Where the time goes
1. Finding and buying the right property. The property has to be zoned for more than one home, outside excluded fire zones and free of recent tenants. Checking that takes weeks.
2. Approval. Under the old path: hearings, appeals and changing conditions. Under the starter home law: a staff review against written rules, with a 60-day clock once the application is complete.
3. Building plan check and permits. Structural, fire, energy and utility reviews. A 2025 law lets builders hire licensed third-party plan checkers when the city misses its 30-day review deadline on small projects.
4. Construction. Foundation, framing, roof, windows, plumbing and electrical, insulation, drywall, finishes. Each stage waits on the last, and each waits on deliveries.
5. Inspections and keys. The city inspects at each stage, then signs off.
Why construction stalls, and how planning fixes it
On most job sites, materials are ordered as the job goes and wood is cut on site. When a delivery is late or a piece doesn’t fit, crews wait. Those gaps add up.
We plan every stud, beam and screw before work starts. The wood is cut to that plan and labeled, and each delivery is timed to arrive as its stage begins: framing first, then roofing and windows, then finishes. The house is still built on site by carpenters, plumbers and electricians, and inspected like any other. It just spends far less time waiting. Read how this compares to modular.
What this means for you as a buyer
If you reserve a Vivienda home, you’ll see the schedule week by week, and you choose your floor plan and finishes before construction begins so nothing changes midway. See the steps.
Questions people ask
What takes longest?
Getting approvals and permits. One study of LA County land sales found that land with an approved permit sells for about 50% more than comparable land without one, mostly because of the time it saves.
Does the starter home law speed things up?
Yes, for qualifying projects. The city has 60 days to act on a complete application, and there's no public hearing.
Do final inspections take long?
A 2025 law (AB 1308) requires agencies to complete final inspections within 10 business days of a completion notice for projects of 10 homes or fewer.